| Project | Baseline period | Reporting period | Normalisation | Evidence | Status | |
|---|---|---|---|---|---|---|
| ARMCONConstruction materials · 🇧🇭 Bahrain | −17%electricity consumption | — | Jun 2020 – Apr 2023 | None | Client letter | Complete |
| Jaber MallRetail · 🇯🇴 Jordan | −16.8%electricity, Jan–May 2026 | Jan 2025 – May 2025 | Jan 2026 – May 2026 | Activity | Utility bills / metering | Complete |
| FUPEL Cía. Ltda.Plastics · 🇪🇨 Ecuador | −16.1%electricity consumption | — | Dec 2022 – Feb 2023 | None | Client letter | Complete |
| Cleaning-services facilityFacility services · 🇧🇪 Belgium | ≈16%lower average hourly consumption, 36 days before vs after | May 27, 2021 – Jul 2, 2021 | Jul 2, 2021 – Aug 8, 2021 | None | Enersol / Denka analysis | Complete |
| Nestlé WatersFood & beverage · 🇯🇴 Jordan | 14.7%average SEC (kWh/m³) reduction, Jul–Aug 2026 — M&V report | Jan 2025 – Jun 2026 | Jul 2026 – Aug 2026 | Production + Pre-install drift | Why® Group M&V✓ Confirmed by the client | Complete |
| Soho HotelHospitality · 🇯🇴 Jordan | −14.3%electricity per point of occupancy, Aug–Oct 2026 | Aug 2025 – Oct 2025 | Aug 2026 – Oct 2026 | Weather & occupancy | Utility bills / metering | Complete |
| HOMAINManufacturing · 🇯🇴 Jordan | −13.8%on the September bill vs. 2025 — no adjustment | Sep 2025 – Oct 2025 | Sep 2026 – Oct 2026 | None | Utility bills / metering | Complete |
| PrintoPackPackaging & printing · 🇸🇦 Saudi Arabia | −11.7%electricity, production-adjusted, Sep–Oct 2026 | Sep 2025 – Oct 2025 | Sep 2026 – Oct 2026 | Production | Utility bills / metering | Interim |
| Al ZohourFood & beverage | −11.0%electricity in September 2026 vs. adjusted baseline | Jan 2026 – Aug 2026 | Sep 2026 | Pre-install drift | Utility bills / metering | Interim |
| PSF Plastic FactoryPlastics · 🇸🇦 Saudi Arabia | −9.2%whole-facility electricity, September 2026 | Jan 2025 – Aug 2026 | Sep 2026 | Production + Pre-install drift | Utility bills / metering | Interim |
| Delivery-services facilityLogistics · 🇧🇪 Belgium | ≈9%lower average hourly consumption, 26-day windows | Jun 7, 2021 – Jul 2, 2021 | Sep 8, 2021 – Oct 3, 2021 | None | Enersol / Denka analysis | Complete |
| Machine-building facilityManufacturing · 🇧🇪 Belgium | ≈8%lower average hourly consumption, 45 days before vs after | Jun 1, 2021 – Jul 15, 2021 | Jul 16, 2021 – Aug 30, 2021 | None | Enersol / Denka analysis | Complete |
| Ciments d’Enfidha (SCE)Cement · 🇹🇳 Tunisia | −7.4%average consumption, kiln motors | Nov 9, 2021 – Dec 6, 2021 | Apr 2, 2022 – Apr 28, 2022 | Production | Signed plant attestation | Complete |
| Cleopatra CementCement · 🇪🇬 Egypt | ≈7.0%raw-mill kWh/t reduction, measured by SGS | — | — | Production | Independent third party | Complete |
| Hospital Santa AnaHealthcare · 🇨🇴 Colombia | ≈3–4%estimated reduction, season-controlled | Jun 2021 – Feb 2022 | Apr 2022 – Jun 2022 | Seasonal model | Enersol / Denka analysis | Complete |
| Saj CeramicsCeramics · 🇰🇪 Kenya | 9.8%harmonic distortion, down from 24.5% (BEST Energy) | — | — | None | Independent third party | Complete |
Cleopatra Cement, Egypt — measured by SGS↗
| Metric | Baseline | With Denka® | Change |
|---|---|---|---|
| Raw-mill specific energy (kWh/t) | 46.88 | 43.76 | ≈ −7.0% |
| Power-draw variance | — | — | 59% improvement |
Nestlé Waters Jordan, Ma'an — M&V by WHY Energy Services Consulting, confirmed by Nestlé Waters↗
| Metric | Baseline | With Denka® | Change |
|---|---|---|---|
| SEC, July 2026 — commissioning (kWh/m³) | 52.08 | 48.38 | −7.1% |
| SEC, August 2026 (kWh/m³) | 57.42 | 45.46 | −20.8% |
| Energy avoided, July–August 2026 | — | 134,693 kWh | −14.7% avg. |
Baseline method: SEC = facility kWh ÷ production m³. Pre-installation SEC rose from 37.74 kWh/m³ (H1 2025) to 46.58 kWh/m³ (H1 2026; February excluded as a maintenance anomaly) — a 23.4% degradation, applied to 2025 summer data to set the expected 2026 baseline. Production: 7,789 m³ (July), 8,853 m³ (August). System online 1 July 2026.
SCOPE
Scope note: these results cover the initial two-month reporting period. The consultant recommends extending M&V to September–October 2026 to confirm the savings stay stable into the autumn shoulder months.
Saj Ceramics, Kenya — BEST Energy site observations
BEST Energy recorded site observations on low-order THD.
SCOPE
Scope note: low-order THD (< 2.5 kHz, IEEE 519) is outside the Denka® design band (150 kHz – 30 MHz). These readings are reported transparently as site observations, not as a primary verified performance metric.
NOTE
Across 100+ facilities worldwide: typically 8–15% reduction in specific energy consumption (kWh/ton), reaching up to ~20% at select sites. Site-specific; verified via IPMVP Option B/C.[15[15] EVO — IPMVPInternational Performance Measurement and Verification Protocol, Options B and C.,16[16] ASHRAE Guideline 14Measurement of energy, demand and water savings.]