Industrial Field Results

Engineering data from deployments of the Black laser-engraved Denka® Platinum Plate.

Field-data explorer

Every published project with its method, so you can weigh the evidence yourself.

16 projects shown

ProjectBaseline periodReporting periodNormalisationEvidenceStatus
ARMCONConstruction materials · 🇧🇭 Bahrain−17%electricity consumption—Jun 2020 – Apr 2023NoneClient letterComplete
Jaber MallRetail · 🇯🇴 Jordan−16.8%electricity, Jan–May 2026Jan 2025 – May 2025Jan 2026 – May 2026ActivityUtility bills / meteringComplete
FUPEL Cía. Ltda.Plastics · 🇪🇨 Ecuador−16.1%electricity consumption—Dec 2022 – Feb 2023NoneClient letterComplete
Cleaning-services facilityFacility services · 🇧🇪 Belgium≈16%lower average hourly consumption, 36 days before vs afterMay 27, 2021 – Jul 2, 2021Jul 2, 2021 – Aug 8, 2021NoneEnersol / Denka analysisComplete
Nestlé WatersFood & beverage · 🇯🇴 Jordan14.7%average SEC (kWh/m³) reduction, Jul–Aug 2026 — M&V reportJan 2025 – Jun 2026Jul 2026 – Aug 2026Production + Pre-install driftWhy® Group M&V✓ Confirmed by the clientComplete
Soho HotelHospitality · 🇯🇴 Jordan−14.3%electricity per point of occupancy, Aug–Oct 2026Aug 2025 – Oct 2025Aug 2026 – Oct 2026Weather & occupancyUtility bills / meteringComplete
HOMAINManufacturing · 🇯🇴 Jordan−13.8%on the September bill vs. 2025 — no adjustmentSep 2025 – Oct 2025Sep 2026 – Oct 2026NoneUtility bills / meteringComplete
PrintoPackPackaging & printing · 🇸🇦 Saudi Arabia−11.7%electricity, production-adjusted, Sep–Oct 2026Sep 2025 – Oct 2025Sep 2026 – Oct 2026ProductionUtility bills / meteringInterim
Al ZohourFood & beverage−11.0%electricity in September 2026 vs. adjusted baselineJan 2026 – Aug 2026Sep 2026Pre-install driftUtility bills / meteringInterim
PSF Plastic FactoryPlastics · 🇸🇦 Saudi Arabia−9.2%whole-facility electricity, September 2026Jan 2025 – Aug 2026Sep 2026Production + Pre-install driftUtility bills / meteringInterim
Delivery-services facilityLogistics · 🇧🇪 Belgium≈9%lower average hourly consumption, 26-day windowsJun 7, 2021 – Jul 2, 2021Sep 8, 2021 – Oct 3, 2021NoneEnersol / Denka analysisComplete
Machine-building facilityManufacturing · 🇧🇪 Belgium≈8%lower average hourly consumption, 45 days before vs afterJun 1, 2021 – Jul 15, 2021Jul 16, 2021 – Aug 30, 2021NoneEnersol / Denka analysisComplete
Ciments d’Enfidha (SCE)Cement · 🇹🇳 Tunisia−7.4%average consumption, kiln motorsNov 9, 2021 – Dec 6, 2021Apr 2, 2022 – Apr 28, 2022ProductionSigned plant attestationComplete
Cleopatra CementCement · 🇪🇬 Egypt≈7.0%raw-mill kWh/t reduction, measured by SGS——ProductionIndependent third partyComplete
Hospital Santa AnaHealthcare · 🇨🇴 Colombia≈3–4%estimated reduction, season-controlledJun 2021 – Feb 2022Apr 2022 – Jun 2022Seasonal modelEnersol / Denka analysisComplete
Saj CeramicsCeramics · 🇰🇪 Kenya9.8%harmonic distortion, down from 24.5% (BEST Energy)——NoneIndependent third partyComplete

Cleopatra Cement, Egypt — measured by SGS↗

MetricBaselineWith Denka®Change
Raw-mill specific energy (kWh/t)46.8843.76≈ −7.0%
Power-draw variance——59% improvement

Nestlé Waters Jordan, Ma'an — M&V by WHY Energy Services Consulting, confirmed by Nestlé Waters↗

MetricBaselineWith Denka®Change
SEC, July 2026 — commissioning (kWh/m³)52.0848.38−7.1%
SEC, August 2026 (kWh/m³)57.4245.46−20.8%
Energy avoided, July–August 2026—134,693 kWh−14.7% avg.

Baseline method: SEC = facility kWh ÷ production m³. Pre-installation SEC rose from 37.74 kWh/m³ (H1 2025) to 46.58 kWh/m³ (H1 2026; February excluded as a maintenance anomaly) — a 23.4% degradation, applied to 2025 summer data to set the expected 2026 baseline. Production: 7,789 m³ (July), 8,853 m³ (August). System online 1 July 2026.

SCOPE
Scope note: these results cover the initial two-month reporting period. The consultant recommends extending M&V to September–October 2026 to confirm the savings stay stable into the autumn shoulder months.

Saj Ceramics, Kenya — BEST Energy site observations

BEST Energy recorded site observations on low-order THD.

SCOPE
Scope note: low-order THD (< 2.5 kHz, IEEE 519) is outside the Denka® design band (150 kHz – 30 MHz). These readings are reported transparently as site observations, not as a primary verified performance metric.
NOTE
Across 100+ facilities worldwide: typically 8–15% reduction in specific energy consumption (kWh/ton), reaching up to ~20% at select sites. Site-specific; verified via IPMVP Option B/C.[15,16]