6 · Diagnostic & M&V Protocol

5-Step Pre-Installation Diagnostic & IPMVP M&V Protocol

Every engagement follows IPMVP Option B/C and ASHRAE Guideline 14. The baseline is measured before installation, and the result is verified on matched production after it.

IPMVP · ASHRAE Guideline 14[15,16]

  1. 01
    Step 1HF noise spectrum survey+

    Clamp an RF current probe around the phase conductors and sweep 2 kHz – 30 MHz with a portable spectrum analyser.

    Instrumentation: Rigol DSA815 / Tektronix RSA306B · RF current probe

  2. 02
    Step 2Thermal baseline+

    Calibrated IR thermography of breaker output terminals, cables and motor terminal boxes.

    Instrumentation: Calibrated IR camera

  3. 03
    Step 3Power-quality baseline+

    Log THD_I, THD_V and true power factor with a Class A analyser, harmonics up to the 50th.

    Instrumentation: Fluke 435-II (Class A)

  4. 04
    Step 4Energy baseline+

    Log active energy (kWh) and production (tons) over a full operating cycle; build a multivariable regression baseline.

    Instrumentation: Revenue-grade metering · regression model

  5. 05
    Step 5Post-installation verification+

    Repeat steps 1–4, plus an ON/OFF/ON (A-B-A) comparison under matched production.

    Instrumentation: IPMVP Option B/C · ASHRAE Guideline 14